LifeCycleCost:Parameters[LINK]
Provides inputs related to the overall life-cycle analysis.
It establishes many of the assumptions used in computing the
present value. It is important that when comparing the results
of multiple simulations that the fields in the LifeCycleCost:Parameters
objects are the same for all the simulations. To aide in this
comparison, the first table in the Life-Cycle Cost Report
shows the inputs to this object. Only one LifeCycleCost:Parameters
object is permitted for a file.
An identifying name used for the LifeCycleCost:Parameters
object.
Field: Discounting
Convention[LINK]
The field specifies if the discounting of future costs
should be computed as occurring at the end of each year, the
middle of each year, or the beginning of each year. The most
common discounting convention uses the end of each year.
Without a specific reason, the end of each year should be
used. Some military projects may specifically require using
the middle of each year. The year being used starts with the
base year and month and repeats every full year. All costs
assumed to occur during that duration are accumulated and
shown as an expense either at the beginning, middle or end of
the year. The options are:
BeginningOfYear
MidYear
EndOfYear
Field: Inflation
Approach[LINK]
This field is used to determine if the analysis should use
constant dollars or current dollars which is related to how
inflation is treated. The two options are:
ConstantDollar
CurrentDollar
The default option is ConstantDollars
If ConstantDollar is selected, then the Real Discount Rate
input is used and it excludes the rate of inflation. If
CurrentDollar is selected, then the Nominal Discount Rate
input is used and it includes the rate of inflation. From NIST
Handbook 135:
“The constant dollar approach has the advantage of avoiding
the need to project future rates of inflation or deflation.
The price of a good or service stated in constant dollars is
not affected by the rate of general inflation. For example, if
the price of a piece of equipment is $1,000 today and $1,050
at the end of a year in which prices in general have risen at
an annual rate of 5 percent, the price stated in constant
dollars is still $1,000; no inflation adjustment is necessary.
In contrast, if cash flows are stated in current dollars,
future amounts include general inflation, and an adjustment is
necessary to convert the current-dollar estimate to its
constant-dollar equivalent. This adjustment is important
because constant- and current-dollar amounts must not be
combined in an LCCA [life cycle cost analysis].”
For most analyses, using the ConstantDollar option will be
easier since the effect of inflation may be ignored.
Field: Real Discount
Rate[LINK]
Enter the real discount rate as a decimal. For a 3% rate,
enter the value 0.03. This input is used when the Inflation
Approach is ConstantDollar. The real discount rate reflects
the interest rates needed to make current and future
expenditures have comparable equivalent values when general
inflation is ignored. When Inflation Approach is set to
CurrentDollar this input is ignored. If this field is blank
and Inflation Approach is ConstantDollar, a warning is
issued.
Field: Nominal Discount
Rate[LINK]
Enter the nominal discount rate as a decimal. For a 5%
rate, enter the value 0.05. This input is used when the
Inflation Approach is CurrentDollar. The real discount rate
reflects the interest rates needed to make current and future
expenditures have comparable equivalent values when general
inflation is included. When Inflation Approach is set to
ConstantDollar this input is ignored. If this field is blank
and Inflation Approach is CurrentDollar, a warning is
issued.
Field: Inflation Rate[LINK]
Enter the rate of inflation for general goods and services
as a decimal. For a 2% rate, enter the value 0.02. If this
field is not blank and Inflation Approach is ConstantDollar, a
warning is issued.
Field: Base Date Month[LINK]
Enter the month that is the beginning of study period, also
known as the beginning of the base period. According to NIST
135 “the base date is the point in time to which all
project-related costs are discounted in an LCCA [life cycle
cost analysis]. The base date is usually the first day of the
study period for the project, which in turn is usually the
date that the LCCA is performed. In a constant dollar
analysis, the base date usually defines the time reference for
the constant dollars (e.g. 1995 constant dollars). It is
essential that you use the same base data and constant-dollar
year for all of the project alternatives to be compared. If
you set the base date to the date that the LCCA is performed,
then the constant dollar basis for the analysis will be the
current date, and you can use actual costs as of that date
without adjusting for general inflation.”
The choices are:
January
February
March
April
May
June
July
August
September
October
November
December
The default value is January.
This field could also be referred to as part of “the date
of study.” It is used as the date for constant dollars.
Field: Base Date Year[LINK]
Enter the four digit year that is the beginning of study
period, such as a year expressed in four digits like “2013”.
The study period is also known as the base period. See more
details in the previous field.
Field: Service Date
Month[LINK]
Enter the month that is the beginning of building
occupancy. Energy costs computed by EnergyPlus are assumed to
occur during the year following the service date. The service
date must be the same or later than the Base Date. The choices
are:
January
February
March
April
May
June
July
August
September
October
November
December
The default value is January. According to NIST Handbook
135:
“The service date is the date on which the project is
expected to be implemented; operating and maintenance costs
(including energy- and water-related costs) are generally
incurred after this date, not before.”
This field could also be referred to as part of “beneficial
occupancy date.”
Field: Service Date Year[LINK]
Enter the four digit year that is the beginning of
occupancy, such as two years after the previously entered
year expressed in four digits like “2013”. See more details in
the previous field.
Field: Length
of Study Period in Years[LINK]
Enter the number of years of the study period. It is the
number of years that the study continues based on the start at
the base date. The default value is 25 years and the maximum
study period is 100 years. Only integers may be used
indicating whole years. According to NIST Handbook 135, “the
study period for an LCCA is the time over which the costs and
benefits related to a capital investment decision are of
interest to the decision maker. Thus, the study period begins
with the base date and includes both the
[planning/construction] period (if any) and the relevant
service period for the project. The service period begins with
the service date and extends to the end of the study
period.”
Field: Tax rate[LINK]
Enter the overall marginal tax rate for the project costs.
This does not include energy or water taxes. The single tax
rate entered here is not intended to be a replacement of the
complex calculations necessary to compute personal or
corporate taxes; instead it is an approximate that may be used
for a simple analysis assuming a constant tax rate is applied
on all costs. The tax rate entered should be based on the
marginal tax rate for the entity and not the average tax rate.
Enter the tax rate results in present value calculations after
taxes. Most analyses do not factor in the impact of taxes and
assume that all options under consideration have roughly the
same tax impact. Due to this, many times the tax rate can be
left to default to zero and the present value results before
taxes are used to make decisions. The value should be entered
as a decimal value. For 15% enter 0.15. For an analysis that
does not include tax impacts, enter 0.0. The default is 0.
Field: Depreciation
Method[LINK]
For an analysis that includes income tax impacts, this
entry describes how capital costs are depreciated. According
to IRS Publication 946 – How to Depreciate Property
“Depreciation is an annual income tax deduction that allows
you to recover the cost or other basis of certain property
over the time you use the property. It is an allowance for
Fair market value the wear and tear, deterioration, or
obsolescence of the Intangible property.” Details on which
depreciation method to choose depends on the property being
depreciated and IRS Publication 946 and your accountant are
the best sources of information in determining which
depreciation method to choose. Only one depreciation method
may be used for an analysis and is applied to all capital
expenditures. Only analyses that include tax impacts need to
select a depreciation method.
The options are:
ModifiedAcceleratedCostRecoverySystem-3year
ModifiedAcceleratedCostRecoverySystem-5year
ModifiedAcceleratedCostRecoverySystem-7year
ModifiedAcceleratedCostRecoverySystem-10year
ModifiedAcceleratedCostRecoverySystem-15year
ModifiedAcceleratedCostRecoverySystem-20year
StraightLine-27year
StraightLine-31year
StraightLine-39year
StraightLine-40year
None
Depreciation allowances reduce the actual/nominal tax
dollars paid by the owner. Thus, analyses using depreciation
should be conducted in nominal dollars. For an analysis that
does not include tax effects, None should be selected.
The default value is None.
An example of this object in an IDF:
LifeCycleCost:Parameters,
TypicalLCC, !- Name
EndOfYear, !- Discounting Convention
ConstantDollar, !- Inflation Approach
0.034314, !- Real Discount Rate
, !- Nominal Discount Rate
, !- Inflation
January, !- Base Date Month
2010, !- Base Date Year
January, !- Service Date Month
2010, !- Service Date Year
25, !- Length of Study Period in Years
0.39, !- Tax rate
StraightLine-39year; !- Depreciation Method
LifeCycleCost:Parameters[LINK]
Provides inputs related to the overall life-cycle analysis. It establishes many of the assumptions used in computing the present value. It is important that when comparing the results of multiple simulations that the fields in the LifeCycleCost:Parameters objects are the same for all the simulations. To aide in this comparison, the first table in the Life-Cycle Cost Report shows the inputs to this object. Only one LifeCycleCost:Parameters object is permitted for a file.
Inputs[LINK]
Field: Name[LINK]
An identifying name used for the LifeCycleCost:Parameters object.
Field: Discounting Convention[LINK]
The field specifies if the discounting of future costs should be computed as occurring at the end of each year, the middle of each year, or the beginning of each year. The most common discounting convention uses the end of each year. Without a specific reason, the end of each year should be used. Some military projects may specifically require using the middle of each year. The year being used starts with the base year and month and repeats every full year. All costs assumed to occur during that duration are accumulated and shown as an expense either at the beginning, middle or end of the year. The options are:
BeginningOfYear
MidYear
EndOfYear
Field: Inflation Approach[LINK]
This field is used to determine if the analysis should use constant dollars or current dollars which is related to how inflation is treated. The two options are:
ConstantDollar
CurrentDollar
The default option is ConstantDollars
If ConstantDollar is selected, then the Real Discount Rate input is used and it excludes the rate of inflation. If CurrentDollar is selected, then the Nominal Discount Rate input is used and it includes the rate of inflation. From NIST Handbook 135:
“The constant dollar approach has the advantage of avoiding the need to project future rates of inflation or deflation. The price of a good or service stated in constant dollars is not affected by the rate of general inflation. For example, if the price of a piece of equipment is $1,000 today and $1,050 at the end of a year in which prices in general have risen at an annual rate of 5 percent, the price stated in constant dollars is still $1,000; no inflation adjustment is necessary. In contrast, if cash flows are stated in current dollars, future amounts include general inflation, and an adjustment is necessary to convert the current-dollar estimate to its constant-dollar equivalent. This adjustment is important because constant- and current-dollar amounts must not be combined in an LCCA [life cycle cost analysis].”
For most analyses, using the ConstantDollar option will be easier since the effect of inflation may be ignored.
Field: Real Discount Rate[LINK]
Enter the real discount rate as a decimal. For a 3% rate, enter the value 0.03. This input is used when the Inflation Approach is ConstantDollar. The real discount rate reflects the interest rates needed to make current and future expenditures have comparable equivalent values when general inflation is ignored. When Inflation Approach is set to CurrentDollar this input is ignored. If this field is blank and Inflation Approach is ConstantDollar, a warning is issued.
Field: Nominal Discount Rate[LINK]
Enter the nominal discount rate as a decimal. For a 5% rate, enter the value 0.05. This input is used when the Inflation Approach is CurrentDollar. The real discount rate reflects the interest rates needed to make current and future expenditures have comparable equivalent values when general inflation is included. When Inflation Approach is set to ConstantDollar this input is ignored. If this field is blank and Inflation Approach is CurrentDollar, a warning is issued.
Field: Inflation Rate[LINK]
Enter the rate of inflation for general goods and services as a decimal. For a 2% rate, enter the value 0.02. If this field is not blank and Inflation Approach is ConstantDollar, a warning is issued.
Field: Base Date Month[LINK]
Enter the month that is the beginning of study period, also known as the beginning of the base period. According to NIST 135 “the base date is the point in time to which all project-related costs are discounted in an LCCA [life cycle cost analysis]. The base date is usually the first day of the study period for the project, which in turn is usually the date that the LCCA is performed. In a constant dollar analysis, the base date usually defines the time reference for the constant dollars (e.g. 1995 constant dollars). It is essential that you use the same base data and constant-dollar year for all of the project alternatives to be compared. If you set the base date to the date that the LCCA is performed, then the constant dollar basis for the analysis will be the current date, and you can use actual costs as of that date without adjusting for general inflation.”
The choices are:
January
February
March
April
May
June
July
August
September
October
November
December
The default value is January.
This field could also be referred to as part of “the date of study.” It is used as the date for constant dollars.
Field: Base Date Year[LINK]
Enter the four digit year that is the beginning of study period, such as a year expressed in four digits like “2013”. The study period is also known as the base period. See more details in the previous field.
Field: Service Date Month[LINK]
Enter the month that is the beginning of building occupancy. Energy costs computed by EnergyPlus are assumed to occur during the year following the service date. The service date must be the same or later than the Base Date. The choices are:
January
February
March
April
May
June
July
August
September
October
November
December
The default value is January. According to NIST Handbook 135:
“The service date is the date on which the project is expected to be implemented; operating and maintenance costs (including energy- and water-related costs) are generally incurred after this date, not before.”
This field could also be referred to as part of “beneficial occupancy date.”
Field: Service Date Year[LINK]
Enter the four digit year that is the beginning of occupancy, such as two years after the previously entered year expressed in four digits like “2013”. See more details in the previous field.
Field: Length of Study Period in Years[LINK]
Enter the number of years of the study period. It is the number of years that the study continues based on the start at the base date. The default value is 25 years and the maximum study period is 100 years. Only integers may be used indicating whole years. According to NIST Handbook 135, “the study period for an LCCA is the time over which the costs and benefits related to a capital investment decision are of interest to the decision maker. Thus, the study period begins with the base date and includes both the [planning/construction] period (if any) and the relevant service period for the project. The service period begins with the service date and extends to the end of the study period.”
Field: Tax rate[LINK]
Enter the overall marginal tax rate for the project costs. This does not include energy or water taxes. The single tax rate entered here is not intended to be a replacement of the complex calculations necessary to compute personal or corporate taxes; instead it is an approximate that may be used for a simple analysis assuming a constant tax rate is applied on all costs. The tax rate entered should be based on the marginal tax rate for the entity and not the average tax rate. Enter the tax rate results in present value calculations after taxes. Most analyses do not factor in the impact of taxes and assume that all options under consideration have roughly the same tax impact. Due to this, many times the tax rate can be left to default to zero and the present value results before taxes are used to make decisions. The value should be entered as a decimal value. For 15% enter 0.15. For an analysis that does not include tax impacts, enter 0.0. The default is 0.
Field: Depreciation Method[LINK]
For an analysis that includes income tax impacts, this entry describes how capital costs are depreciated. According to IRS Publication 946 – How to Depreciate Property “Depreciation is an annual income tax deduction that allows you to recover the cost or other basis of certain property over the time you use the property. It is an allowance for Fair market value the wear and tear, deterioration, or obsolescence of the Intangible property.” Details on which depreciation method to choose depends on the property being depreciated and IRS Publication 946 and your accountant are the best sources of information in determining which depreciation method to choose. Only one depreciation method may be used for an analysis and is applied to all capital expenditures. Only analyses that include tax impacts need to select a depreciation method.
The options are:
ModifiedAcceleratedCostRecoverySystem-3year
ModifiedAcceleratedCostRecoverySystem-5year
ModifiedAcceleratedCostRecoverySystem-7year
ModifiedAcceleratedCostRecoverySystem-10year
ModifiedAcceleratedCostRecoverySystem-15year
ModifiedAcceleratedCostRecoverySystem-20year
StraightLine-27year
StraightLine-31year
StraightLine-39year
StraightLine-40year
None
Depreciation allowances reduce the actual/nominal tax dollars paid by the owner. Thus, analyses using depreciation should be conducted in nominal dollars. For an analysis that does not include tax effects, None should be selected.
The default value is None.
An example of this object in an IDF:
Documentation content copyright © 1996-2026 The Board of Trustees of the University of Illinois and the Regents of the University of California through the Ernest Orlando Lawrence Berkeley National Laboratory. All rights reserved. EnergyPlus is a trademark of the US Department of Energy.